Camden coal seam gas well rehabilitation program

AGL has released our schedule for the rehabilitation of coal seam gas wells over the next two years at our Camden Gas Project.

In February this year we announced that the existing gas production facility at Camden will close in 2023 and the site and associated wells will be progressively decommissioned and rehabilitated. Camden has been safely supplying gas to Sydney homes and businesses since 2001. A total of 144 wells have been drilled, with 92 currently producing.

Rehabilitation work commenced in 2016, with six wells having been completed and a further 17 to undergo rehabilitation in 2017. 41 of the original 144 gas wells will have been rehabilitated at the completion of Stage One of the program.

Further information and the Stage One well rehabilitation program can be found in our media release.